With most of the excavation work for the 30" cooling water duct complete, the team has been busy fabricating, coating, and starting installation on a large underground network of pipe.

30" HDPE cooling water pipe is fabricated above ground before installation

Installation of coated pipe
Nearby, the crew is busy erecting a portion of the bag house, giving a sense of what's to come.

Bag house is erected adjacent to the electric arc furnace
Made in the U.S.A. for more than 100 years