For the first time since Steel Talk started, we are able to go into the caster building. There, the crew is working on the foundation and formwork for the caster cooling table.

Caster cooling table area construction progress

 

We are also getting a first look at the entry scale foundation work at the scrap yard.  Trucks carrying loads of scrap metal will go through this weight system to determine its weight and content.

 

Foundation work on the scrap yard entry scale

 