For the first time since Steel Talk started, we are able to go into the caster building. There, the crew is working on the foundation and formwork for the caster cooling table.

Caster Cooling Table 072019a

Caster cooling table area construction progress

 

We are also getting a first look at the entry scale foundation work at the scrap yard.  Trucks carrying loads of scrap metal will go through this weight system to determine its weight and content.

 

Scrap Yard Entry Scale 072019

Foundation work on the scrap yard entry scale

 

If you haven't done so, please subscribe to receive updates right in your email. Simply fill out the form at the top of this page and you can begin receiving new blog posts!

Topics: Electric Arc Furnace, Fairfield Tubular Operations, Alabama, EAF

Blog Home

Subscribe to Receive Updates

Recent Posts

Welcome to Steel Talk!

We will share exciting news periodically here and encourage you to check back and share information to those that might be interested.